Article 23 Additional requirements to be met by heating control measures

Original text. Later amendments are not shown.

A heating control measure meets the requirements of this article if it—

(a)

is installed at the same domestic premises where an ECO4A qualifying action that is an insulation measure has been installed (“the related insulation measure”);

(b)

is completed—

(i)

on the same day as, or not more than three months after, the day on which the related insulation measure is completed; and

(ii)

after the pre-installation energy efficiency assessment is performed; and

(c)

is promoted by the same participant who promoted the related insulation measure.