# The Electricity and Gas (Energy Efficiency Obligations) Order 2001, Article 10: Information as to compliance


(1) The Authority may, by notice in writing, require a supplier which is at any time between 1 April 2002 and 31 March 2005 subject to an energy efficiency obligation under this Order to give to the Authority, within such period as may be specified in the notice, such information as to the steps taken by the supplier to comply with its obligation as the Authority may reasonably require.
(2) Without prejudice to the generality of paragraph (1), the Authority may require the provision of information as to—
(a) the steps that the supplier has taken in relation to the total activity or any scheme notified under article 7;
(b) any material change in the details notified in accordance with article 7(2)(b);
(c) the energy savings achieved by the total activity or scheme;
(d) the percentage of those savings that has been achieved in relation to those of its domestic consumers who are in receipt of a benefit described in Schedule 2;
(e) the carbon savings achieved by the total activity or scheme;
(f) the cost of the total activity to the supplier’s domestic consumers; and
(g) where the total activity or scheme took the form of the installation of a number of units—
(i) the total number of units installed;
(ii) the type of dwellings in which the units were installed; and
(iii) whether those dwellings were owner-occupied or rented and, if rented, whether from a social landlord or a private landlord.

---
Source: https://www.legislation.gov.uk/ukdsi/2001/0110388852/article/10 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-efficiency-obligations-order-2001/article-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.