Paragraph 17
(1)
Article 51 (general provisions) is amended as follows.
(2)
For paragraph 1 substitute—
“1.Subject to paragraph 2, the regulatory authority’s published criteria for granting derogations pursuant to Articles 52 and 53 which applied immediately before IP completion day continue to apply on and after IP completion day, and the regulatory authority must continue to publish those criteria (including any subsequent amendments) on its website.”.
(3)
In paragraph 2, for “in accordance with paragraph 1” substitute “after consulting relevant system operators, power generating facility owners and other stakeholders who it considers may be affected by this Regulation”.