# The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019, Paragraph 11


(1) Article 12 (information relating to the use of cross-zonal capacities) is amended as follows.
(2) In paragraph 1—
(a) for “provide” substitute “publish”;
(b) omit “to the ENTSO for Electricity”; and
(c) omit point (h).
(3) In paragraph 2, omit point (g).

---
Source: https://www.legislation.gov.uk/ukdsi/2019/9780111179895/schedule/3/paragraph/11 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-market-integrity-and-transparency-amendment-eu-exit-regulations-2019/schedule-3/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.