# The Electricity Capacity (Amendment) Regulations 2015, Paragraph 19: Regulation 73 (consequences of successful review or appeal)


(1) For regulation 73(6)(b) substitute—
“(b) for—
(i) the de-rated capacity of the CMU (which, if not previously determined, must be determined by the Delivery Body in accordance with capacity market rules); or
(ii) in the case of a demand side response CMU, the capacity (if less than that de-rated capacity) nominated by the applicant for the purposes of this paragraph (ii) in accordance with capacity market rules;”.
(2) After regulation 73(6) insert—
“(6A) The capacity nominated for the purposes of paragraph (6)(b)(ii) is to be treated as the DSR bid capacity for purposes of regulations 32 and 60.”.

---
Source: https://www.legislation.gov.uk/ukdsi/2015/9780111127452/schedule/1/paragraph/19 (the official version)
Page: https://openlegislation.uk/draft-electricity-capacity-amendment-regulations-2015/schedule-1/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.