# The Electricity Capacity (Amendment) Regulations 2015, Paragraph 4: Regulation 14 (eligibility to bid in capacity auctions)


(1) In regulation 14(1), for “An applicant” substitute “Subject to paragraph (3), an applicant”.
(2) After regulation 14(2) insert—
“(3) In respect of an interconnector CMU, an applicant is not eligible to bid in a capacity auction held for a delivery year commencing before 2019.”.

---
Source: https://www.legislation.gov.uk/ukdsi/2015/9780111127452/schedule/1/paragraph/4 (the official version)
Page: https://openlegislation.uk/draft-electricity-capacity-amendment-regulations-2015/schedule-1/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.