Regulation 4 Amendment to regulation 11 (meaning of auction parameters)
In regulation 11—
in paragraph (1)(e), after “15 year minimum £/kW threshold” insert “, 9 year minimum £/kW threshold”;
in paragraph (3)—
for “In paragraph (1)”, substitute “In this regulation”;
for the definitions of “15 year minimum £/kW threshold” and “3 year minimum £/kW threshold” substitute—
““3 year minimum £/kW threshold” means the minimum amount of capital expenditure per kilowatt of de-rated capacity which a bidder must commit to spending on a generating CMU or an unproven demand side response CMU that is not a three year zero capex threshold CMU to be eligible to bid for a capacity obligation for a period of 2 or 3 delivery years;
“9 year minimum £/kW threshold” means the minimum amount of capital expenditure per kilowatt of de-rated capacity which a bidder must commit to spending on a declared low carbon CMU that is a new build CMU, a refurbishing CMU or an unproven demand side response CMU to be eligible to bid for a capacity obligation for a period of more than 3 and up to 9 delivery years;
“15 year minimum £/kW threshold” means the minimum amount of capital expenditure per kilowatt of de-rated capacity which a bidder must commit to spending—
- (a)
on a declared low carbon CMU that is a generating CMU or an unproven demand side response CMU to be eligible to bid for a capacity obligation for a period of more than 9 and up to 15 delivery years; or
- (b)
on any other generating CMU or unproven demand side response CMU to be eligible to bid for a capacity obligation for a period of more than 3 and up to 15 delivery years;”;
after the definition of “auction target capacity”, insert—
“; and
“declared low carbon CMU”, “new build CMU”, “refurbishing CMU”, and “three year zero capex threshold CMU” have the meaning given in the Rules.”.