In regulation 11—

(a)

in paragraph (1)(e), after “15 year minimum £/kW threshold” insert “, 9 year minimum £/kW threshold”;

(b)

in paragraph (3)—

(i)

for “In paragraph (1)”, substitute “In this regulation”;

(ii)

for the definitions of “15 year minimum £/kW threshold” and “3 year minimum £/kW threshold” substitute—

  • ““3 year minimum £/kW threshold” means the minimum amount of capital expenditure per kilowatt of de-rated capacity which a bidder must commit to spending on a generating CMU or an unproven demand side response CMU that is not a three year zero capex threshold CMU to be eligible to bid for a capacity obligation for a period of 2 or 3 delivery years;

  • “9 year minimum £/kW threshold” means the minimum amount of capital expenditure per kilowatt of de-rated capacity which a bidder must commit to spending on a declared low carbon CMU that is a new build CMU, a refurbishing CMU or an unproven demand side response CMU to be eligible to bid for a capacity obligation for a period of more than 3 and up to 9 delivery years;

  • “15 year minimum £/kW threshold” means the minimum amount of capital expenditure per kilowatt of de-rated capacity which a bidder must commit to spending—

    1. (a)

      on a declared low carbon CMU that is a generating CMU or an unproven demand side response CMU to be eligible to bid for a capacity obligation for a period of more than 9 and up to 15 delivery years; or

    2. (b)

      on any other generating CMU or unproven demand side response CMU to be eligible to bid for a capacity obligation for a period of more than 3 and up to 15 delivery years;”;

(iii)

after the definition of “auction target capacity”, insert—

“; and

  • “declared low carbon CMU”, “new build CMU”, “refurbishing CMU”, and “three year zero capex threshold CMU” have the meaning given in the Rules.”.