Regulation 10 Return of supplier charge payments: agreement termination trigger event
If the agreement termination trigger event and T-1 termination trigger event have both occurred, the Settlement Body must, for each electricity supplier (“S”), as soon as reasonably practicable after both trigger events have occurred—
determine the amount of supplier charge and any other payments paid by S which it holds under regulation 7(1) on the day on which the trigger event occurs;
determine the amount of interest payable (if any) on the amount determined under sub-paragraph (a); and
make a payment to S for an amount determined by adding the amounts determined under sub-paragraphs (a) and (b).
In paragraph (1)(b), interest is payable only if there is a legal obligation to pay S interest in respect of the amount determined under paragraph (1)(a), and is only payable to the extent of that legal obligation.