In regulation 43A (non-completion fee) of the Principal Regulations, after paragraph (5), insert—
“(6) Regulation 33 applies (except for paragraphs (2)(b), (3) and (5)(b)) to a non-completion notice as it applies to a termination notice, and for that purpose, a reference in regulation 33 to—
(a) a “termination fee” is to be construed as a reference to a non-completion fee; and
(b) a “termination notice” is to be construed as a reference to a non-completion notice.”.

---