# The Electricity Capacity (No. 1) Regulations 2019, Regulation 27: Non-completion fees: modifications


(1) The modifications in paragraph (2) apply in respect of—
(a) the conditional agreement auction, including the rights and obligations arising out of, or in relation to, this auction; and
(b) capacity agreements that existed on 15th November 2018.
(2) Regulation 43A (non-completion fee) of the Principal Regulations applies as if in paragraph (6)—
(a) in paragraph (a), “; and” were omitted;
(b) in paragraph (b), for “.” there were inserted “; and”; and
(c) after paragraph (b), there were inserted—
“(c) if a non-completion notice is issued during the standstill period, a direction to the Delivery Body to withdraw the termination notice and to terminate a capacity agreement on the ground specified in capacity market rules is to be construed as a reference to a direction to the Delivery Body to withdraw the non-completion notice.”.

---
Source: https://www.legislation.gov.uk/ukdsi/2019/9780111182437/regulation/27 (the official version)