# The Electricity Capacity (No. 1) Regulations 2019, Regulation 58: Penalty residual supplier amount: modifications


Regulation 8 (penalty residual supplier amount) of the Supplier Payment Regulations applies as if—
(a) at the beginning of paragraph (3), there were inserted “Subject to paragraph (3A),”; and
(b) after paragraph (3), there were inserted—
“(3A) If year X is the delivery year beginning on 1st October 2018, the reference in paragraph (3) to “the 28th working day after the end of each delivery year” is to be construed as a reference to “the 28th working day after the end of the delivery year (if a payment trigger event occurs before that date) or otherwise as soon as reasonably practicable after a payment trigger event occurs.”.

---
Source: https://www.legislation.gov.uk/ukdsi/2019/9780111182437/regulation/58 (the official version)
Page: https://openlegislation.uk/draft-electricity-capacity-no-1-regulations-2019/regulation-58
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.