# The Electricity Capacity Regulations 2014, Regulation 15: General eligibility criteria


(1) The Delivery Body must not prequalify a CMU for a capacity auction unless it meets the general eligibility criteria.
(2) The general eligibility criteria for a CMU are the conditions specified in paragraphs (3) to (5).
(3) The first condition is that the CMU is in Great Britain or the offshore area.
(4) The second condition is that the connection capacity of the CMU is equal to or greater than 2MW (the “minimum capacity threshold”).
(5) The third condition is that the CMU is not an CMU which, by virtue of regulations 16 to 18, the Delivery Body must not prequalify for a capacity auction.

---