# The Electricity Capacity Regulations 2014, Regulation 17: Excluded capacity: NER 300 and CCS grant scheme CMUs


(1) The Delivery Body must not prequalify a CMU (“CMU i”) unless the applicant has provided to it, by the close of the prequalification window, a declaration in writing that no relevant grant has been, or will be, paid in respect of CMU i.
(2) In this regulation—
“relevant grant” means a grant under a relevant scheme, the first payment of which is made, or to be made, within the period of 10 years immediately before the commencement of the delivery period; and
“relevant scheme” means a scheme of financial assistance provided under—
(a) NER 300;
(b) section 1(1) of the Energy Act 2010 in respect of a CCS demonstration project within the meaning of that section; or
(c) section 5(1) of the Science and Technology Act 1965 to support carbon capture and storage.
(3) In paragraph (2), “NER 300” means the competition established under Article 10a(8) of Directive 2003/87/EC of the European Parliament and of the Council establishing a scheme for greenhouse gas emission allowance trading within the Community and amending Council Directive 96/61/EC.

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111116852/regulation/17 (the official version)
Page: https://openlegislation.uk/draft-electricity-capacity-regulations-2014/regulation-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.