Regulation 25 Notification of results
The Delivery Body must, after a capacity auction is completed—
as soon as reasonably practicable notify the auction results to the Secretary of State;
within one working day, give notice to each bidder of whether or not its bid was a successful bid; and
within 8 working days, publish the auction results.
In paragraph (1) “the auction results” means—
the auction clearing price;
the total amount of capacity in respect of which successful bids were made;
the CMUs in respect of which successful bids were made;
in respect of each such CMU—
the de-rated capacity of the CMU, and, in the case of a demand side response CMU, its DSR bid capacity if different; and
the duration of capacity obligation for which, and the price at which, the successful bid was made.
In paragraphs (1) and (2), a “successful bid” means a bid that, subject to regulation 27, results in the award of a capacity obligation to the bidder.