  "heading": "The settlement calculations",
  "text": "(1) The Settlement Body must make the calculations set out in this Part and Schedule 1 (the “settlement calculations”)—\n(a) by such date as may be specified or, where no date is specified, by such time as is necessary to enable the Settlement Body to comply with the regulations in this Part; and\n(b) so far as possible, using the required data.\n(2) Where, by the time a settlement calculation is to be made, the Settlement Body has not been provided with any required data which is necessary for that calculation, the calculation must be made using the best data available to the Settlement Body.\n(3) In this regulation, “required data” means data which is required to be provided to the Settlement Body under capacity market rules.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/ukdsi/2014/9780111116852/regulation/36",
    "retrieved_at": "2026-10-30T15:12:43.570912+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}