# The Electricity Capacity Regulations 2014, Paragraph 1: Interpretation


(1) In this Schedule “ A E ij ”, “ ALFC O ij ” and “ E ij ”, in relation to a capacity committed CMU and a relevant settlement period, are to be interpreted in accordance with regulation 39 and mean the amounts determined in accordance with that regulation.
(2) Where, in a formula, two values in parentheses are separated by a comma and preceded by “min”, that means that the lesser of those two values is to be used in making the calculation.

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111116852/schedule/1/paragraph/1 (the official version)
Page: https://openlegislation.uk/draft-electricity-capacity-regulations-2014/schedule-1/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.