# The Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024, Regulation 7: Regulation 2 (interpretation)


In regulation 2(1)—
(a) in the appropriate places insert the following definitions—
““CM EII excluded electricity” means any amount of electricity determined as such in accordance with regulation 3 of the CM Excluded Electricity Regulations;
“CM Excluded Electricity Regulations” means the Electricity Capacity (Supplier Payment etc.) (Amendment and Excluded Electricity) Regulations 2024;”;
““relevant arrangements” means arrangements which are approved by the Settlement Body under paragraph (2) or (3)(a) of regulation 4 of the CM Excluded Electricity Regulations;
“relevant demand” in relation to an electricity supplier (“S”) means the amount of electricity (expressed in MWh) supplied by S to premises in Great Britain;”;
(b) omit the definition of “gross demand”.

---
Source: https://www.legislation.gov.uk/ukdsi/2024/9780348256758/regulation/7 (the official version)