# The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019, Paragraph 102


(1) Article 157 is amended as follows.
(2) In paragraph 2—
(a) omit points (a) to (c), (h) and (i);
(b) in point (j), for the second sentence, substitute—
“The sharing agreement for the GB synchronous area shall require that the positive reserve capacity on FRR and the risk of non-delivery due to sharing shall be assessed continually by the TSOs of the LFC block.”;
(c) in point (k), for the second sentence, substitute—
“The sharing agreement shall require that the negative reserve capacity on FRR and the risk of non-delivery due to sharing shall be assessed continually by the TSOs of the LFC block.”.

---
Source: https://www.legislation.gov.uk/ukdsi/2019/9780111179857/schedule/1/paragraph/102 (the official version)
Page: https://openlegislation.uk/draft-electricity-network-codes-and-guidelines-system-operation-and-connection-amendment-etc-eu-exit-regulations-2019/schedule-1/paragraph-102
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.