OpenLegislation

Regulation 16 Amendment of the ESO Regulations (Regulation 4)

Original text. Later amendments are not shown.

(1)

Regulation 4 of the ESO Regulations is amended as follows.

(2)

In paragraph (1)—

(a)

for the formula substitute—

“”

(GP−CP)×[ SDS−( XE+GE ) TDS−( TE+GT ) ]
(b)

after the definition of SDS insert—

  • “XE is the amount of EII excluded electricity supplied by that supplier on that day;

  • GE is the amount of green excluded electricity supplied by that supplier in that quarterly obligation period divided by the number of days in that period;”

(c)

after the definition of TDS insert—

  • “TE is the total amount of EII excluded electricity supplied by all suppliers on that day;

  • GT is the total amount of green excluded electricity supplied by all suppliers in that quarterly obligation period divided by the number of days in that period.”.