# The Environmental Permitting (England and Wales) Regulations 2007, Interpretation of Part A(1)


(a) Melting, including making alloys, of non-ferrous metals, including recovered products (refining, foundry casting, etc.) where—
(i) the plant has a melting capacity of more than 4 tonnes per day for lead or cadmium or 20 tonnes per day for all other metals, and no furnace (other than a vacuum furnace), bath or other holding vessel used in the plant for the melting has a design holding capacity of 5 or more tonnes; or
(ii) the plant uses a vacuum furnace of any design holding capacity.

---
Source: https://www.legislation.gov.uk/ukdsi/2007/9780110788760/schedule/1/part/2/chapter/2/crossheading/nonferrous-metals-interpretation-of-part-a1 (the official version)
Page: https://openlegislation.uk/draft-environmental-permitting-england-and-wales-regulations-2007/schedule-1/part-2/chapter-2/crossheading-nonferrous-metals-interpretation-of-part-a1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.