Paragraph 5 Public participation: scope
Paragraph 6 applies to every application for the grant of an environmental permit except an application in relation to—
mobile plant; or
a standard facility, unless the facility is a Part A installation.
Paragraph 6 applies to every application to vary an environmental permit if—
it would entail a substantial change; or
the regulator determines that the paragraph should apply.
Paragraph 8 applies to every regulator initiated variation if—
it would entail a substantial change; or
the regulator determines that the paragraph should apply.
But, paragraphs 6 and 8 do not apply to the extent that the application or regulator initiated variation relates to—
the burning of waste oil in an appliance with a rated thermal input of less than 0.4 megawatts;
dry cleaning;
the unloading of petrol into stationary storage tanks at a service station if it is an activity within paragraph (d) of Part B of Section 1.2 of Part 2 of Schedule 1; or
any motor vehicle refuelling activity within paragraph (e) or (f) of Part B of Section 1.2 of Part 2 of Schedule 1.
In this paragraph—
-
“change in operation” means a change in the nature or functioning, or an extension, of an installation, which may have consequences for the environment;
-
“co-incineration plant” has the meaning given in Section 5.1 of Part 2 of Schedule 1;
-
“dry cleaning” has the meaning given in Part B of Section 7 of Part 2 of Schedule 1;
-
“incineration plant” has the meaning given in Section 5.1 of Part 2 of Schedule 1;
-
“substantial change” means a change in operation of an installation which in the regulator’s opinion may have significant negative effects on human beings or the environment and includes—
- (a)
in relation to a Part A installation, a change in operation which in itself meets the thresholds, if any, set out in Part 2 of Schedule 1, and
- (b)
in relation to an incineration plant or co-incineration plant for non-hazardous waste, a change in operation which would involve the incineration or co-incineration of hazardous waste.
- (a)
When assessing whether a change in operation of a Part B installation has significant effects on the environment, the regulator must consider only its emissions to air.