# The Environmental Permitting (England and Wales) Regulations 2016, Paragraph 6: Change in operation


(1) Operators holding environmental permits for installations to which this Schedule applies must notify the regulator of any substantial change in the operation of that installation.
(2) Where there is a substantial change in the operation of an installation, the regulator must ensure that the environmental permit is reviewed and, if necessary, updated.

---
Source: https://www.legislation.gov.uk/ukdsi/2016/9780111150184/schedule/8/paragraph/6 (the official version)