# The Greenhouse Gas Emissions Trading Scheme (Amendment) (No. 2) Order 2024, Article 24: Article 60A inserted


After article 60 insert—
“Installations: failure to submit information under article 27A
60A. (1) The operator of an installation is liable to a civil penalty where the operator fails to comply (or to comply on time) with the requirements of article 27A.
(2) The civil penalty is—
(a) £5,000; and
(b) a daily penalty at a daily rate of £500 for each day that the operator fails to comply with the requirements of article 27A, beginning with the day on which the initial notice is given, up to a maximum of £45,000.”.

---