# The Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025, Regulation 9: Requirement to provide written summary following investigation


(1) This regulation applies following a relevant investigation unless—
(a) the relevant investigation identifies required work, and
(b) the required work is completed before the end of the relevant period.
(2) The lessor must, before the end of the relevant period, give the lessee a document setting out the information specified in paragraph (3).
(3) The following is the specified information—
(a) where the investigation was an emergency, standard or renewed investigation—
(i) whether or not the investigation identified a significant hazard or emergency hazard, and
(ii) where such a hazard was identified, what that hazard is;
(b) where further action is required under these Regulations, what that action is and a target timescale for beginning and completing the action;
(c) where sub-paragraph (b) does not apply, that there is no further action required under these Regulations, and the reasons why;
(d) information about how the lessee may contact the lessor.
(4) In this regulation, “the relevant period” means the period of 3 working days beginning on the day after the day on which the relevant investigation is completed

---
Source: https://www.legislation.gov.uk/ukdsi/2025/9780348273083/regulation/9 (the official version)
Page: https://openlegislation.uk/draft-hazards-in-social-housing-prescribed-requirements-england-regulations-2025/regulation-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.