OpenLegislation

Regulation 4 Maximum Amount of Waste sent to Landfill from England in Non-target years

Original text. Later amendments are not shown.

The maximum amount by weight of biodegradable municipal waste allowed in a scheme year mentioned in Table 2 to be sent to landfills from England shall be in accordance with that Table.

Table 2

Scheme YearMaximum Amount (in tonnes)
1st Yearf115,200,000
2nd Year14,530,000
3rd Year13,640,000
4th Year12,530,000

Annotations

Footnotes

f1

As a result of the amendment to the Act made by regulation 2, the 1st scheme year for England will begin on 1st April 2005 and end on 31 March 2006. The 2nd and subsequent scheme years will follow this cycle. Therefore the 2nd scheme year will begin on 1st April 2006, the 3rd scheme year on 1st April 2007 and the 4th scheme year on 1st April 2008.