# The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005, Paragraph 5


Where so required by the engineer the Executive shall to the reasonable satisfaction of the engineer fence off a specified work or a protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from a waterway, whether on a temporary or permanent basis or both.

---
Source: https://www.legislation.gov.uk/ukdsi/2005/0110723244/schedule/11/crossheading/fencing/paragraph/5 (the official version)
Page: https://openlegislation.uk/draft-midland-metro-wednesbury-to-brierley-hill-and-miscellaneous-amendments-order-2005/schedule-11/crossheading-fencing/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.