OpenLegislation

Regulation 37 Transitional provision

Original text. Later amendments are not shown.

(1)

In the case of a qualifying nuclear facility existing immediately before amendment day, the operator must declare to the ONR the design information for the qualifying nuclear facility, using the relevant questionnaire shown in Part 1 of Schedule 1 of the 2019 Regulations, before the end of the period of three years beginning with amendment day.

(2)

In the case of a qualifying nuclear facility existing immediately before amendment day, for a period of one year beginning with amendment day—

(a)

Part 1 of Schedule 1 to the 2019 Regulations is to be treated as if no amendment was made by these Regulations;

(b)

references to “design information” in the 2019 Regulations are to be treated as references to “basic technical characteristics”.

(3)

In this regulation—

  • “the 2019 Regulations” means the Nuclear Safeguards (EU Exit) Regulations 2019;

  • “amendment day” means the day on which these Regulations come into force.