Regulation 4 Programme of activities
An operator of a qualifying nuclear facility must send to the ONR an annual outline programme of activities using the information described in Part 8 of Schedule 1, indicating, in particular, provisional dates for taking a physical inventory.
Each year, an operator must send the annual outline programme of activities for the following calendar year to the ONR so that it is received by the ONR by 30th September.
An operator must inform the ONR of the programme of activities for the taking of a physical inventory at least 40 days before the day on which the physical inventory is taken.
An operator must communicate to the ONR without delay a change which affects or may affect the outline programme of activities and, in particular, the taking of physical inventories.