Regulation 17 General information relating to pipelines
This regulation applies to the following information relating to a pipeline in respect of which the OGA has granted a pipeline works authorisation—
the design of the pipeline;
the capacity of the pipeline;
the route of the pipeline;
the geographic coordinates for the points at which the pipeline begins and ends and any points at which it changes direction;
the maximum allowable operating pressure of the pipeline;
the things authorised to be conveyed by the pipeline;
the burial status of the pipeline;
the average depth of the pipeline below sea level;
the dates on which construction of the pipeline started and finished or is expected to start and finish.
Where this regulation applies, the OGA (or a subsequent holder) may publish the information after the date on which the OGA grants the pipeline works authorisation.