OpenLegislation

Production of Cement and Lime Production of Cement and Lime

Original text. Later amendments are not shown.

  1. (a)

    Producing or grinding cement clinker.

  2. (b)

    Producing lime—

    1. (i)

      in kilns or other furnaces with a production capacity of more than 50 tonnes per day; or

    2. (ii)

      where the activity is likely to involve the heating in any period of 12 months of 5,000 tonnes or more of calcium carbonate or calcium magnesium carbonate or, in aggregate, of both.