Paragraph 6
In this Part of this Schedule—
-
“determination date” means—
- (a)
for an installation, part of an installation or mobile plant in relation to which a permit is granted, the date on which it is granted, whether in pursuance of the application for the permit or, on an appeal, of a direction to grant it;
- (b)
for an installation, part of an installation or mobile plant in relation to which a permit is refused and the applicant for the permit appeals against the refusal, the date of the affirmation of the refusal;
- (c)
for an installation, part of an installation or mobile plant in relation to which a permit is refused and no appeal is made against the refusal, the date immediately following the last day, determined in accordance with paragraph 2 of Schedule 8, on which notice of appeal might have been given.
- (a)
-
“existing” means, in relation to a Part A installation or a Part A mobile plant—
- (a)
an installation or mobile plant which is put in to operation before 31st October 1999; or
- (b)
an installation or mobile plant which is put into operation on or after that date but before 31st October 2000, provided that—
- (i)
the operation of the installation or mobile plant was authorised by the relevant authorisation before 31st October 1999; or
- (ii)
an application for such authorisation was duly made before that date;
- (i)
- (a)
-
“new” means, in relation to a Part A installation or a Part A mobile plant, an installation or plant which is put into operation on or after 31st October 1999 other than an existing Part A installation or Part A mobile plant;
-
“relevant authorisation” means, in relation to the operation of a Part A installation or Part A mobile plant—
- (a)
where the operation of the installation or mobile plant immediately before 31st October 1999 requires an authorisation under Part I of the Environmental Protection Act 1990, an authorisation under that Part of that Act;
- (b)
where the operation of the installation or mobile plant immediately before 31st October 1999 requires a waste management licence under Part II of the Environmental Protection Act 1990, a waste management licence under that Part of that Act;
- (c)
in any other case, planning permission granted under the Town and Country Planning Act 1990;
- (a)
-
“relevant period” shall be interpreted in accordance with paragraph 2.