# The Pollution Prevention and Control (Scotland) Regulations 2012, Regulation 45: Permits: proposed change in operation


(1) An operator of an installation or mobile plant in respect of which a permit is granted must give notice to SEPA of a proposed change in operation (a “change notice”) at least 14 days before making the change.
(2) A change notice must—
(a) be in writing, and
(b) contain a description of the proposed change in operation.
(3) SEPA must acknowledge receipt of a change notice.
(4) A change notice is not necessary if—
(a) the operator applies for a variation of the permit before a change in operation is made, and
(b) that application describes the proposed change.
(5) An operator must not make a change during any period beginning with the date of service on the operator of a notice under regulation 63(2) and ending on the date on which the operator provides the required information.

---
Source: https://www.legislation.gov.uk/sdsi/2012/9780111018514/regulation/45 (the official version)
Page: https://openlegislation.uk/draft-pollution-prevention-and-control-scotland-regulations-2012/regulation-45
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.