# The Procurement Act 2023 (Consequential and Other Amendments) Regulations 2025, Regulation 34: Transitional provision in respect of the Health Care Services (Provider Selection Regime) Regulations 2023


(1) Nothing in regulation 28 (amendment of the Health Care Services (Provider Selection Regime) Regulations 2023) affects—
(a) any contract award procedure commenced, but not yet awarded, before 24th February 2025;
(b) any contract awarded in accordance with the Health Care Services (Provider Selection Regime) Regulations 2023 (“the 2023 Regulations”) before—
(i) 24th February 2025, or
(ii) on or after that date but where the award itself was not, by virtue of sub-paragraph (a), affected by these Regulations;
(c) the conclusion of any framework agreement where the procurement process commenced, but where the framework agreement was not concluded, before 24th February 2025;
(d) any framework agreement concluded in accordance with the 2023 Regulations—
(i) before 24th February 2025, or
(ii) on or after that date but where the conclusion of the framework agreement was not, by virtue of sub-paragraph (c), affected by these Regulations.
(2) For the purposes of paragraph (1)—
(a) a contract award procedure has been commenced before 24th February 2025 if, before that date—
(i) a relevant authority has contacted a provider in order to commence Direct Award Process A or Direct Award Process B;
(ii) notice of intention to make an award under Direct Award Process C has been submitted to the UK e-notification service for publication in accordance with regulation 9 (Direct Award Process C) of the 2023 Regulations;
(iii) notice of intention to follow the Most Suitable Provider Process has been submitted to the UK e-notification service for publication in accordance with regulation 10 (the Most Suitable Provider Process) of the 2023 Regulations;
(iv) notice inviting offers in accordance with the Competitive Process has been submitted to the UK e-notification service for publication in accordance with regulation 11 (the Competitive Process) of the 2023 Regulations;
(b) the procurement process for a framework agreement has been commenced before the 24th February 2025 if, before that date, notice inviting offers in accordance with the Competitive Process has been submitted to the UK e-notification service for publication in accordance with regulation 11 of the 2023 Regulations.
(3) In this regulation—
(a) the following have the same meaning as in the 2023 Regulations—
(i) Competitive Process;
(ii) Direct Award Process A;
(iii) Direct Award Process B;
(iv) Direct Award Process C;
(v) framework agreement;
(vi) Most Suitable Provider Process;
(vii) provider;
(viii) UK e-notification service;
(b) “relevant authority” has the same meaning as in section 12ZB(7) of the National Health Service Act 2006.

---
Source: https://www.legislation.gov.uk/ukdsi/2025/9780348267181/regulation/34 (the official version)
Page: https://openlegislation.uk/draft-procurement-act-2023-consequential-and-other-amendments-regulations-2025/regulation-34
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

