# The Railways (Interoperability in Northern Ireland) (Convention on International Carriage by Rail) (Amendment) Regulations 2026, Regulation 6: Application for authorisation for a fixed installation


(1) An application for an authorisation for a fixed installation to be placed in service must be made to the DFI and be accompanied by—
(a) evidence of the safe integration of the subsystems, established on the basis of the relevant TSIs, notified national rules and the common safety methods,
(b) evidence of the technical compatibility of the subsystems with the subsystem into which they are being integrated, established on the basis of the relevant TSIs, notified national rules and relevant registers,
(c) the technical file compiled in accordance with regulation 21(5),
(d) an EC declaration of verification, and
(e) in the case of trackside control-command and signalling subsystems involving European Train Control System equipment or Global System for Mobile Communications – Railway equipment—
(i) evidence of the approval decision of the European Union Agency for Railways issued in accordance with regulation 7, and
(ii) where there has been a change to the draft tender specifications or to the description of the envisaged technical solutions that occurred after the approval decision, evidence of compliance with the result of the procedure referred to in Article 30 (2) of the Agency Regulation.
(2) Subject to paragraph (3), in considering an application the DFI must not require checks already carried out under the EC verification assessment procedure to be carried out again.
(3) The DFI may require such additional checks which it considers necessary in relation to the fixed installation if that fixed installation appears to the DFI not to meet the essential requirements.
(4) Where additional checks are required under paragraph (3) the DFI must—
(a) inform the applicant that the application cannot be determined before the additional checks are carried out, and
(b) notify the European Commission in writing as soon as reasonably practicable of any such additional checks it requires and the reasons for requiring those checks.
(5) Within the period of one month beginning with the day after the day on which the application is received, the DFI must respond in writing and confirm—
(a) that the application is complete, or
(b) what supplementary information is required for the completion of the file, together with a reasonable deadline for providing it.

---
Source: https://www.legislation.gov.uk/ukdsi/2026/9780348284874/regulation/6 (the official version)
Page: https://openlegislation.uk/draft-railways-interoperability-in-northern-ireland-convention-on-international-carriage-by-rail-amendment-regulations-2026/regulation-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.