For article 29(2) of the 2009 Order substitute—

“(2)

The amount of electricity to be stated in each ROC issued in respect of electricity generated—

(a)

by a generating station to which this article applies, and

(b)

using—

(i)

pre-2013 capacity,

(ii)

2013/14 capacity, or

(iii)

2014/15 capacity,

is 1 2 of a megawatt hour.

(3)

The amount of electricity to be stated in each ROC issued in respect of electricity generated—

(a)

by a generating station to which this article applies, and

(b)

using 2015/16 capacity,

is 10 19 of a megawatt hour.

(4)

The amount of electricity to be stated in each ROC issued in respect of electricity generated—

(a)

by a generating station to which this article applies, and

(b)

using post-2016 capacity,

is 5 9 of a megawatt hour.

(5)

This article is subject to article 32.”.