# The Renewables Obligation (Amendment) Order 2013, Article 26: Amount of electricity to be stated in ROCs issued for electricity generated using 2013/14 capacity, 2014/15 capacity, 2015/16 capacity or post-2016 capacity


After Part 2 of Schedule 2 to the 2009 Order insert—
“PART 2A
AMOUNT OF ELECTRICITY TO BE STATED IN ROCs ISSUED FOR ELECTRICITY GENERATED USING 2013/14 CAPACITY, 2014/15 CAPACITY, 2015/16 CAPACITY OR POST-2016 CAPACITY
Articles 27(5) to (8), (10) and 33(3)
Generation type
Amount of electricity (in megawatt hours) to be stated in a ROC issued for electricity generated using—
2013/14 capacity
2014/15 capacity
2015/16 capacity
post-2016 capacity
AD
1 2
1 2
10 19
5 9
Advanced gasification/
pyrolysis
1 2
1 2
10 19
5 9
Building mounted solar PV
10 17
5 8
2 3
5 7
Closed landfill gas
5
5
5
5
Co-firing of regular bioliquid
2
2
2
2
Dedicated biomass
2 3
2 3
2 3
5 7
Dedicated energy crops
1 2
1 2
10 19
5 9
Electricity generated from sewage gas
2
2
2
2
Energy from waste with CHP
1
1
1
1
Geopressure
1
1
1
1
Geothermal
1 2
1 2
10 19
5 9
Ground mounted solar PV
5 8
5 7
10 13
5 6
High-range co-firing
10 9
10 9
10 9
10 9
Hydroelectric
10 7
10 7
10 7
10 7
Landfill gas heat recovery
10
10
10
10
Low-range co-firing
2
2
2
2
Mid-range co-firing
5 3
5 3
5 3
5 3
Offshore wind
1 2
1 2
10 19
5 9
Onshore wind
10 9
10 9
10 9
10 9
Standard gasification/
pyrolysis
1 2
1 2
10 19
5 9
Station conversion
1
1
1
1
Tidal impoundment – tidal barrage
1 2
1 2
10 19
5 9
Tidal impoundment – tidal lagoon
1 2
1 2
10 19
5 9
Tidal stream
1 2
1 2
1 2
1 2
Unit conversion
1
1
1
1
Wave
1 2
1 2
1 2
1 2
PART 2B
AMOUNT OF ELECTRICITY TO BE STATED IN ROCs ISSUED FOR ELECTRICITY GENERATED USING PRE-2013 CAPACITY OR 2013/15 CAPACITY WHERE ARTICLE 28(3) OR (4) APPLIES
Article 28(3) and (4)
Generation type
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the qualifying proportion of electricity generated using pre-2013 capacity or 2013/15 capacity
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the remainder of the electricity generated using pre-2013 capacity or 2013/15 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
1 2
2 3
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1
PART 2C
AMOUNT OF ELECTRICITY TO BE STATED IN ROCS ISSUED FOR ELECTRICITY GENERATED USING 2015/16 CAPACITY WHERE ARTICLE 28(5) APPLIES
Article 28(5)
Generation type
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the qualifying proportion of electricity generated using 2015/16 capacity
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the remainder of the electricity generated using 2015/16 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
10 19
2 3
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1
PART 2D
AMOUNT OF ELECTRICITY TO BE STATED IN ROCS ISSUED FOR ELECTRICITY GENERATED USING POST-2016 CAPACITY WHERE ARTICLE 28(6) APPLIES
Article 28(6)
Generation type
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the qualifying proportion of electricity generated using post-2016 capacity
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the remainder of the electricity generated using post-2016 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
5 9
5 7
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1
”

---
Source: https://www.legislation.gov.uk/ukdsi/2013/9780111534137/article/26 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-amendment-order-2013/article-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.