# The Renewables Obligation and Electricity Capacity (Amendment) (British Industrial Competitiveness Scheme Excluded Electricity) Regulations 2026, Regulation 8: BICS determinations: relevant proportion of electricity


(1) The relevant proportion of electricity in relation to a BICS determination is calculated in accordance with this regulation.
(2) If all the electricity supplied to the electricity meters in respect of a manufacturing site is used in the course of business by the BICS applicant and none of it is electricity in respect of which an EII certificate is in force, the proportion under paragraph (1) is—
(a) zero, if the relevant electricity is 25% or less of the total amount of electricity measured by those meters;
(b) 50%, if the relevant electricity is more than 25% but less than 50% of the total amount of electricity measured by those meters;
(c) 100%, if the relevant electricity is 50% or more of the total amount of electricity measured by those meters.
(3) In this regulation, “relevant electricity” means the sum of—
(a) the amount of electricity used for a specified activity in the course of the business of the BICS applicant, and
(b) the qualifying amount of electricity used for a related activity in the course of the business of the BICS applicant, calculated in accordance with paragraph (4),
but excluding any electricity in respect of which an EII certificate is in force.
(4) The qualifying amount of electricity used for a related activity is—
(a) zero, if 25% or less of the electricity used for the related activity is attributable to a specified activity;
(b) 50% of the total amount of electricity used for the related activity, if more than 25% but less than 50% of the electricity used for that activity is attributable to a specified activity;
(c) 100% of the total amount of electricity used for the related activity, if 50% or more of the electricity used for that activity is attributable to a specified activity.
(5) If all the electricity supplied to the electricity meters in respect of a manufacturing site is used in the course of business by the BICS applicant but some of it is electricity in respect of which an EII certificate is in force, the proportion under paragraph (1) is—
TIER x (100%-A)
where—
TIER is the proportion that would be specified under paragraph (1) in accordance with paragraph (2) if none of the electricity supplied to the electricity meters in respect of a manufacturing site was electricity in respect of which an EII certificate was in force, expressed as 0, 50 or 100, as the case may be, and
A is the proportion of electricity in respect of which an EII certificate is in force.
(6) If electricity measured by a meter in respect of a manufacturing site is shared with another person and none of the electricity used by the BICS applicant is electricity in respect of which an EII certificate is in force, the proportion to be specified under paragraph (1) is to be calculated in accordance with the formula—
TIER × PROP
where—
TIER is the proportion that would be specified under paragraph (1) in accordance with paragraph (2) if all the electricity supplied to the electricity meters in respect of a manufacturing site was used in the course of business by the BICS applicant expressed as 0, 50 or 100, as the case may be, and
PROP is the proportion of electricity measured by the meter which is used by the BICS applicant, expressed as a percentage.
(7) If electricity measured by a meter in respect of a manufacturing site is shared with another person and some of the electricity used by the BICS applicant is electricity in respect of which an EII certificate is in force, the proportion to be specified under paragraph (1) is to be calculated in accordance with the formula—
TIER x (100%-A) x PROP
where—
TIER is the proportion that would be specified under paragraph (1) in accordance with paragraph (2) if all the electricity supplied to the electricity meters in respect of a manufacturing site was used in the course of business by the BICS applicant and none of it was electricity in respect of which an EII certificate was in force, expressed as 0, 50 or 100, as the case may be,
PROP is the proportion of electricity measured by the meter which is used by the BICS applicant, expressed as a percentage, and
A is the proportion of electricity in respect of which an EII certificate is in force.
(8) For the purposes of paragraphs (6) and (7), if—
(a) more than one person makes a BICS application in relation to the meter in respect of a manufacturing site that is shared with another person, and
(b) the evidence under regulation 7(1)(l)(ii) contained in the BICS applications taken together indicates that the sum of the proportion of the electricity measured by that meter that was used in the course of the BICS applicants’ businesses exceeds 100%,
the proportion of electricity measured by that meter which is used by each BICS applicant is to be determined by the Secretary of State, by reference to the evidence provided under regulation 7(1)(l) and any further information as the Secretary of State may reasonably require, so that the sum of those proportions does not exceed 100%.

---
Source: https://www.legislation.gov.uk/ukdsi/2026/9780348286762/regulation/8 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-and-electricity-capacity-amendment-british-industrial-competitiveness-scheme-excluded-electricity-regulations-2026/regulation-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.