Article 2 Interpretation
In this Order—
-
“accredited” is to be construed in accordance with the definition of “accreditation” in article 2 of the Renewables Obligation Order 2009f1;
-
“CHPQA 3” means the Combined Heat and Power Quality Assurance Standard, Issue 3, published by the Department for Environment, Food and Rural Affairs in January 2009f2;
-
“CHPQA 5” means the Combined Heat and Power Quality Assurance Standard, Issue 5, published by the Department of Energy and Climate Change in November 2013f3;
-
“commission” and “commissioned” are to be construed in accordance with the definition of “commissioned” in article 2 of the Renewables Obligation Order 2009;
-
“grid works”, in relation to a generating station, means—
- (a)
the construction of a connection between the station and a transmission or distribution system for the purpose of enabling electricity to be conveyed from the station to that system, or
- (b)
the carrying out of modifications to a connection between the station and a transmission or distribution system for the purpose of enabling an increase in the amount of electricity that can be conveyed over that connection from the station to that system;
- (a)
-
“network operator” means a distribution exemption holder, distribution licence holder or a transmission licence holder;
-
“original capacity”, in relation to a generating station, means the generating capacity of the station as accredited;
-
“radar works” means—
- (a)
the construction of a radar station,
- (b)
the installation of radar equipment,
- (c)
the carrying out of modifications to a radar station or to radar equipment, or
- (d)
the testing of a radar station or radar equipment;
- (a)
-
“relevant date” means the later of—
- (a)
31st October 2014, and
- (b)
the date falling two months after the day on which this Order comes into force; and
- (a)
-
“relevant fossil fuel generating station” has the same meaning as in Schedule 2 to the Renewables Obligation Order 2009f4.
In this Order, the following have the same meaning as in the Renewables Obligation Order 2009f5—
-
“biomass”;
-
“energy crops”;
-
“permitted ancillary purposes”;
-
“regular biomass”;
-
“waste”.
Annotations
Footnotes
- f1
-
S.I. 2009/785 as amended by S.I. 2010/1107, S.I. 2011/984, paragraph 29 of Schedule 4 to S.I. 2011/988, S.I. 2013/768 and S.I. 2014/893. Article 2 of S.I. 2009/785 has been amended by article 2 of S.I. 2013/768. There are other amendments to article 2 which are not relevant.
- f2
-
Copies can be obtained from the Department of Energy and Climate Change, 3 Whitehall Place, London, SW1A 2AW and are available at http://chpqa.decc.gov.uk/chpqa-documents.
- f3
-
Copies can be obtained from the Department of Energy and Climate Change, 3 Whitehall Place, London, SW1A 2AW and are available at http://chpqa.decc.gov.uk/chpqa-documents.
- f4
-
Schedule 2 to S.I. 2009/785 has been amended by article 17 of S.I. 2011/984 and article 24 of S.I. 2013/768. There are other amendments which are not relevant.
- f5
-
See article 2(1) of S.I. 2009/785 (as amended by article 2 of S.I. 2013/768).