Article 6 Large onshore wind generating stations accredited, or additional capacity added, on or before 31stMarch 2017: approved development condition met
(1)
The circumstances set out in this Article are where the electricity is—
(a)
generated using the original capacity of a large onshore wind generating station—
(i)
which was accredited on or before 31st March 2017, and
(ii)
in respect of which the approved development condition is met, or
(b)
generated using additional capacity of a large onshore wind generating station, where—
(i)
the station was accredited on or before 31st March 2016,
(ii)
in the Authority’s view, the additional capacity first formed part of the station on or before 31st March 2017, and
(iii)
the approved development condition is met in respect of the additional capacity.