Paragraph 26 applies, where in respect of any generating station, the operator—

(a)

has given notice under a NIRO Order which, had that notice been given in respect of a station to which article 21 applies, would have constituted notice under article 21(2); and

(b)

has not done anything that, had it been done in respect of a station to which article 21 applies, would have constituted withdrawal of that notice under article 21(5).