# The Renewables Obligation Order 2009, Article 11: Determining the total number of renewables obligation certificates to be produced in an obligation period


(1) Having completed calculations A, B and C for an obligation period, the Secretary of State is to determine the total number of renewables obligation certificates required to be produced by designated electricity suppliers (“the total obligation”) for that period in accordance with paragraphs (2) to (5).
(2) Where calculation A is greater than calculation B for an obligation period, the total obligation for that period is calculation A.
(3) Subject to paragraph (4), where calculation B is greater than calculation A for an obligation period, the total obligation for that period is calculation B.
(4) Where calculation B is greater than calculations A and C for an obligation period, the total obligation for that period is calculation C.
(5) References to the total obligation in article 12 are to be construed accordingly.

---
Source: https://www.legislation.gov.uk/ukdsi/2009/9780111473955/article/11 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-order-2009/article-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.