# The Renewables Obligation Order 2015, Article 54: Large hydro generating stations first commissioned on or before 1st April 2002


(1) ROCs are not to be issued in respect of any electricity generated by a large hydro generating station if the station was first commissioned on or before 1st April 2002.
(2) In this article, “large hydro generating station” means a hydro generating station which has, or has had at any time since 1st April 2002, a declared net capacity of more than 20 megawatts.

---
Source: https://www.legislation.gov.uk/ukdsi/2015/9780111138359/article/54 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-order-2015/article-54
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.