# The Renewables Obligation Order 2015, Article 63: Circumstances in which ROCs must not be issued in respect of electricity generated from solid or gaseous biomass


(1) This article applies to biomass (other than animal excreta, bioliquid, landfill gas, sewage gas or waste).
(2) ROCs are not to be issued in respect of any electricity generated by a generating station from biomass to which this article applies unless—
(a) the generating station has a total installed capacity of less than 1 megawatt, or
(b) the biomass meets the greenhouse gas criteria and the land criteria.

---