# The Renewables Obligation Order 2015, Article 67: Payments to discharge the renewables obligation


(1) A designated electricity supplier may (in whole or in part) discharge its renewables obligation for an obligation period (“the relevant period”) by making a payment to the Authority before the 1st September in the following obligation period (“the settlement period”).
(2) The payment referred to in paragraph (1) is an amount equal to £X × (Y − Z) where—
(a) X is the sum which corresponds to a UK ROC by virtue of paragraph (4);
(b) Y is the number of UK ROCs that the designated electricity supplier, if it makes no payment under paragraph (1), would have to produce to the Authority in order for it to discharge its renewables obligation for the relevant period in full; and
(c) Z is the number of UK ROCs that it has produced to the Authority for that period (or, where it has not produced any, zero).
(3) Where a designated electricity supplier makes a payment to the Authority which is less than the amount calculated under paragraph (2), its renewables obligation for the relevant period will be discharged by that payment to the extent of the appropriate number of UK ROCs, which is the quotient obtained by dividing the payment made by the sum which corresponds to a UK ROC by virtue of paragraph (4).
(4) The sum which corresponds to a UK ROC (“the buy-out price”) is—
(a) for the relevant period commencing with 1st April 2016, £44.33 increased or, as the case may be, decreased by the percentage increase or decrease in the retail prices index over the 12 month period ending with 31st December 2015 (the resulting figure being rounded to the nearest penny, with any half of a penny being rounded upwards), and
(b) for each obligation period thereafter, the buy-out price for the previous obligation period increased or, as the case may be, decreased by the percentage increase or decrease in the retail prices index over the 12 month period ending with the 31st December in the previous obligation period (the resulting figure being rounded to the nearest penny, with any half of a penny being rounded upwards).

---
Source: https://www.legislation.gov.uk/ukdsi/2015/9780111138359/article/67 (the official version)