# The Renewables Obligation Order 2015, Part 3: AMOUNT OF ELECTRICITY TO BE STATED IN ROCs ISSUED FOR ELECTRICITY GENERATED USING 2013/14 CAPACITY, 2014/15 CAPACITY, 2015/16 CAPACITY OR POST-2016 CAPACITY


Way of generating electricity
Amount of electricity (in megawatt hours) to be stated in a ROC issued for electricity generated using—
2013/14 capacity
2014/15 capacity
2015/16 capacity
post-2016 capacity
AD
1 2
1 2
10 19
5 9
Advanced gasification/ pyrolysis
1 2
1 2
10 19
5 9
Building mounted solar PV
10 17
5 8
2 3
5 7
Closed landfill gas
5
5
5
5
Co-firing of regular bioliquid
2
2
2
2
Dedicated biomass
2 3
2 3
2 3
5 7
Dedicated energy crops
1 2
1 2
10 19
5 9
Electricity generated from sewage gas
2
2
2
2
Energy from waste with CHP
1
1
1
1
Geopressure
1
1
1
1
Geothermal
1 2
1 2
10 19
5 9
Ground mounted solar PV
5 8
5 7
10 13
5 6
High-range co-firing
10 9
10 9
10 9
10 9
Hydroelectric
10 7
10 7
10 7
10 7
Landfill gas heat recovery
10
10
10
10
Low-range co-firing
2
2
2
2
Mid-range co-firing
5 3
5 3
5 3
5 3
Offshore wind
1 2
1 2
10 19
5 9
Onshore wind
10 9
10 9
10 9
10 9
Standard gasification/ pyrolysis
1 2
1 2
10 19
5 9
Station conversion
1
1
1
1
Tidal impoundment
1 2
1 2
10 19
5 9
Tidal stream
1 2
1 2
1 2
1 2
Unit conversion
1
1
1
1
Wave
1 2
1 2
1 2
1 2

---
Source: https://www.legislation.gov.uk/ukdsi/2015/9780111138359/schedule/5/part/3 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-order-2015/schedule-5/part-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.