# The Renewables Obligation Order 2015, Part 7: AMOUNT OF ELECTRICITY TO BE STATED IN ROCs ISSUED FOR ELECTRICITY GENERATED USING POST-2016 CAPACITY WHERE ARTICLE 35(6) APPLIES


Way of generating electricity
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the qualifying proportion of electricity generated using post-2016 capacity
Amount of electricity (in megawatt hours) to be stated in a ROC issued in respect of the remainder of the electricity generated using post-2016 capacity
Co-firing of regular bioliquid with CHP
1
2
Dedicated biomass with CHP
5 9
5 7
High-range co-firing with CHP
5 7
10 9
Low-range co-firing with CHP
1
2
Mid-range co-firing with CHP
10 11
5 3
Station conversion with CHP
2 3
1
Unit conversion with CHP
2 3
1

---
Source: https://www.legislation.gov.uk/ukdsi/2015/9780111138359/schedule/5/part/7 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-order-2015/schedule-5/part-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.