# The Renewables Obligation Order (Northern Ireland) 2009, Article 7: Part of calculation A referable to Northern Ireland


(1) Before the start of each obligation period identified in the first column of Schedule 1, (except for the first such period), the Department is to estimate, in megawatt hours, the total amount of electricity likely to be supplied to customers in Northern Ireland during that period by electricity suppliers designated under this Order.
(2) The figure representing the number of megawatt hours so estimated for an obligation period is to be multiplied by the figure which corresponds to that period in the third column of Schedule 1.

---