# The Renewables Obligation (Scotland) Amendment Order 2013, Article 14: Microgenerators


For article 29(2) (microgenerators) substitute—
“(2) The amount of electricity to be stated in each SROC issued in respect of electricity generated—
(a) by a generating station to which this article applies; and
(b) using—
(i) pre-2013 capacity;
(ii) 2013/14 capacity; or
(iii) 2014/15 capacity,
is 1 2 of a megawatt hour.
(3) The amount of electricity to be stated in each SROC issued in respect of electricity generated—
(a) by a generating station to which this article applies; and
(b) using 2015/16 capacity,
is 10 19 of a megawatt hour.
(4) The amount of electricity to be stated in each SROC issued in respect of electricity generated—
(a) by a generating station to which this article applies; and
(b) using post-2016 capacity,
is 5 9 of a megawatt hour.
(5) This article is subject to article 32.”.

---
Source: https://www.legislation.gov.uk/sdsi/2013/9780111019542/article/14 (the official version)
Page: https://openlegislation.uk/draft-renewables-obligation-scotland-amendment-order-2013/article-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.