Article 27 Substitution of Part2 of Schedule2
For Part 2 of Schedule 2 (amount of electricity to be stated in SROCs generally) substitute—
“PART 2
AMOUNT OF ELECTRICITY TO BE STATED IN SROCs ISSUED FOR ELECTRICITY GENERATED USING PRE-2013 CAPACITY
Articles 27(4) and (9) and 33(3)
Generation type Amount of electricity (in megawatt hours) to be stated in a SROC issued for electricity generated using pre-2013 capacity AD Advanced gasification/pyrolysis Co-firing of regular bioliquid 2 Dedicated biomass Dedicated energy crops Electricity generated from landfill gas 4 Electricity generated from sewage gas 2 Energy from waste with CHP 1 Enhanced tidal stream Enhanced wave Geopressure 1 Geothermal High-range co-firing Hydroelectric 1 Low-range co-firing 2 Mid-range co-firing Offshore wind Onshore wind 1 Solar photovoltaic Standard gasification/pyrolysis 1 Station conversion 1 Tidal impoundment – tidal barrage Tidal impoundment – tidal lagoon Tidal stream Unit conversion 1 Wave ”