If—

(a)

by reason of the construction of any tidal work or dredging it is reasonably necessary for Forth Ports to incur costs in temporarily or permanently altering, removing, re-siting, repositioning or reinstating existing moorings or aids to navigation (including navigation marks or lights) owned by Forth Ports, or laying down and removing replacement moorings or buoys, or carrying out dredging operations for any such purpose, not being costs which it would have incurred for any other reason; and

(b)

Forth Ports gives the Company not less than 28 days’ notice of its intention to incur such costs, and takes into account any representations which the Company may make in response to the notice within 14 days of the receipt of the notice,

the Company shall pay the costs reasonably so incurred by Forth Ports.